Skills on MM: Material Management

2007 ( 7 months ) Patek Philippe: support end-users after go-live on MM/PP

Support end-user in requirements definition or issue description. Build and document the solution in helpdesk tool and in project base.

Upgrade: test and document all the possible flows to make the knowledge transfer easier to local IS team.

Examples of my new builds:

2002 ( 4 months ) for Capgemini capitalisation / internal project S@me agro:

Project: build pre-customized for small enterprise in agro food industry .

I have been appointed referent consultant for master data.

This internal project enable me to fine tune my knowledge on batch management and on traceability required for expiry date.

2000/2001 ( 7 months) Antalis (Switzerland) / project "Aries"

Design, build, test, document project on following scope:

- all MRP planning procedures and forecast based on past consumption.
- stock transfers and inter company
- third party processing and ATP with multi plant check

I worked on this project up to get the key-user acceptance on the integration test I wrote.

2000 (6 months) Parke Davis on PP/MM

Black fill the key-user who resigned 6 months before planned go live of Core System

- define and run the unit tests and integration test on stock management and subcontracting
- end-user training to the solution
- authorization management

1999 (3 months) Pechiney CRV (Research center) on MM

Pre and post go live assistance:

- define and run unit tests and integration test; finalize customizing on purchasing and on MRP et d'intégration; finalisation du paramétrage MM Achat et MRP.
- end-user training and after go live assistance providing